Before you sign with Rzian Homez you see the full bill of quantities, the nine payment stages, the 270-day programme and the warranty terms. This page shows the shape of each, so there is nothing to discover later.

01

The bill of quantities comes first

Every Rzian Homez home is priced from an itemised bill of quantities (BOQ) that you receive before the work agreement is signed. The BOQ lists what is built, from what, and in what quantity. It is the document the contract points to, so the three commitments beside it can be written plainly.

The sample below is structure only. Rates, quantities and totals are specific to each project and are shared with you privately.

What the contract commits to
Extra works outside the BOQ are quoted separately, in writing, before they are executed.
Items not in the BOQ are not part of the contract. If it is not written down, it is not promised.
The final cost is held within plus or minus five percent of the contracted value.

What a Rzian Homez BOQ contains

SectionWhat is itemisedSpecification anchor
1Site preparation, excavation, earthworkSoil report reference
2Foundation and plinthStructural drawing reference; cement and reinforcement grades and approved manufacturers as specified in the structural design and BOQ
3Superstructure: walls, columns, beams, slabsStructural drawing reference; M-Sand or P-Sand
4Roofing and waterproofingNamed system and warranty period
5Doors and windowsDoor and window materials as specified in the BOQ
6Flooring and wall finishesTile range and rate band
7Plumbing and sanitarywareJaquar, Grohe or Kohler; fitting schedule
8ElectricalPoint schedule, named wire and switch brands
9Painting and external finishesNamed paint system
10Exclusions and client-supplied itemsListed explicitly, one line each
02

Nine payment stages, each tied to work you can see

Payments follow construction, not the calendar. Each stage is released only after the milestone that names it is complete on site. The amount attached to each stage is set out in your payment schedule, which you receive with the BOQ.

Building permits and statutory approvals are the client's responsibility under the work agreement. We advise, and we can recommend liaison agents.

1Site visit and assessment (an advance, adjusted into stage 3)
2Memorandum of understanding signed
3Work agreement signed, BOQ attached
4Plinth beam complete
5Ground-floor slab cast
6First-floor slab cast
7Plastering complete
8Tiling complete
9Handover
03

The 270-day programme

Construction runs to a 270-day programme from start of construction to handover. It is the standard Rzian Homez programme and is written into the work agreement, with the stage schedule attached. The agreement also sets out the circumstances that can affect the programme, including approved changes and other project-specific conditions. The signed work agreement governs extensions, variations and project-specific conditions.

04

Warranty

CoverPeriodWhat it covers
Structural warranty5 years from handoverThe structure of the home as built by Rzian Homez under the work agreement.
Service warranty1 year from handoverWorkmanship on the work carried out under the BOQ.

Manufacturer warranties on named products, such as sanitaryware from Jaquar, Grohe or Kohler, roofing and waterproofing systems and paint systems, pass to you at handover with their documentation where applicable, and run for the period the supplier states.

Residential interiors

Interiors contracted with Rzian Homez carry a one-year service warranty on workmanship. Parts and materials are covered according to the applicable supplier or manufacturer warranty, handed over with the project documentation.

The signed work agreement and handover warranty document govern the detailed warranty terms and claim process.

What is outside the contract

Land, boundary and title matters.
Building permit, KMBR or KPBR approvals and utility connections (client responsibility under the work agreement; we advise and can recommend liaison agents).
Anything not itemised in the BOQ.
Interiors, unless contracted separately with Rzian Homez.

Ask any builder you are comparing for the same three documents: an itemised BOQ before signing, a milestone-linked payment schedule, and the warranty terms in writing.